92 &102 Day 20 Progress (Tue)

It is now nearly three weeks since ground works commenced on PCPs 92 and 102.  Civil engineering work, including completion of the power connections was finished at the start of last week, and from the outside both cabinets now look ready for service.  However there are still a number of tasks ongoing.

102_fibre
Openreach engineer jointing new fibre run to PCP102 in Popley Way

On Friday (day 16) Openreach engineers were installing fibre to PCP102.  This, and a similar run to PCP92 were due to be completed over the next few days, allowing commissioning and testing of the cabinets to proceed.

WP_20151119_15_44_10_Pro
102 fibre twin complete
WP_20151119_15_50_43_Pro
92 fibre twin complete