For much of the day, there was little progress on either site. A team arrived in the morning, and re-instated the pavements, initially at PCP92, and then at PCP102. For the former, this was in preparation for the roadworks being shifted to the other side of the road to complete the trenching to a suitable power cable jointing location, as otherwise both pavements would have been out of service concurrently.
However late in the afternoon the VDSL2 cabinet shell for PCP 102 was delivered and installed, which is another great step forward in the project.
PCP102
PCP 102 FTTC Install Day 5, pavement re-instated but before the FTTC shell was installedPCP 102 FTTC Install Day 5, leaves and mud starting to tarnish the nice green cabinet floor!PCP 102 FTTC Install Day 5, telecom ducting into the core-drilled pavement chamber still to be completed (from day 1)PCP 102 FTTC Install Day 5
And with a hat on…
PCP 102 FTTC Install Day 5 – cabinet shell in place!It’s arrived! PCP 102 FTTC Install Day 5 – cabinet shell in place!Nicely in line with the existing PCP102, unlike the pavement location at PCP92The cabinet now even comes pre-installed with the power warning – but alas there is no power connected – yet!
PCP92
PCP 92 FTTC Install Day 5, pavement re-instated around the cabinet basePCP 92 FTTC Install Day 5PCP 92 FTTC Install Day 5, pavement re-instated, allowing work to move to the other side of the carriagewayPCP 92 FTTC Install Day 5PCP 92 FTTC Install Day 5, cabinet base surrounded by fresh tarmacPCP 92 FTTC Install Day 5