92 &102 Day 2 Progress (Friday)

PCP 102

Having completed the power duct, cabinet foundation, the majority of the telecom ducting, and core-drilled the existing pavement chamber on Thursday, work focused on PCP92 on Friday.  Below are some photos in daylight after the first day:

IMAG5279
PCP102 FTTC install day 2
IMAG5273
PCP102 FTTC install day 2
IMAG5271
PCP102 FTTC install day 2
IMAG5274
PCP102 FTTC install day 2

 

PCP 92

Whilst the cabinet foundation for PCP92 was laid on the first day of work, the ducting did not progress far.  The work team completed the telecom ducting to the pavement chamber on Friday, and then progressed across the road carriageway, completing half, in search of power.

IMAG5284
PCP92 FTTC install day 2 – power duct works
IMAG5287
PCP92 FTTC install day 2 – power duct works
IMAG5292
PCP92 FTTC install day 2 – comms ducting complete
IMAG5293
PCP92 FTTC install day 2 – power duct works across the carriageway
IMAG5295
PCP92 FTTC install day 2

 